The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard

The following data for a pottery company pertain to the production of 2,000 clay pots during July.

Direct Materials (all materials purchased were used):

Standard cost: $2.00 per kilogram of clay

Total actual cost: $10,640

Standard cost allowed for units produced was $12,000

Materials quantity variance was $800 favourable

Direct Manufacturing Labour:

Standard cost is 2 pots per hour at $24.00 per hour

Actual cost per hour was $24.50

Actual labour was 1028 hours

What is the materials price variance?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Sivaramakrishna, Ramji Balakrishnan

1st Edition

0471467855, 978-0471467854

More Books

Students also viewed these Accounting questions

Question

Why are stereotypes so resistant to change?

Answered: 1 week ago

Question

Speak clearly and distinctly with moderate energy

Answered: 1 week ago

Question

Get married, do not wait for me

Answered: 1 week ago