The following data is given for the Bahia Company: Budgeted production 1,064 units Actual production 958 units Materials: Standard price per pound $1.864 Standard pounds

  1. The following data is given for the Bahia Company:

    Budgeted production 1,064 units
    Actual production 958 units
    Materials:
    Standard price per pound $1.864
    Standard pounds per completed unit 10
    Actual pounds purchased and used in production 9,293
    Actual price paid for materials $19,051
    Labor:
    Standard hourly labor rate $14.25 per hour
    Standard hours allowed per completed unit 4.6
    Actual labor hours worked 4,933.7
    Actual total labor costs $75,239
    Overhead:
    Actual and budgeted fixed overhead $1,162,000
    Standard variable overhead rate $27.00 per standard labor hour
    Actual variable overhead costs $138,144
    Overhead is applied on standard labor hours.

    The variable factory overhead controllable variance is

    a.$115,763.16 unfavorable

    b.$115,763.16 favorable

    c.$19,160.40 unfavorable

    d.$19,160.40 favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ebook Principles Of Financial Accounting

Authors: John Wild, Ken Shaw, Barbara Chiappetta

2nd Edition

0077166183, 9780077166182

More Books

Students also viewed these Accounting questions