The following data is given for the Stringer Company: Budgeted production 26,000 units Actual production 27,500 units Materials: Standard price per ounce $6.50 Standard ounces
The following data is given for the Stringer Company:
Budgeted production | 26,000 units |
Actual production | 27,500 units |
Materials: | |
Standard price per ounce | $6.50 |
Standard ounces per completed unit | 8 |
Actual ounces purchased and used in production | 228,000 |
Actual price paid for materials | $1,504,800 |
Labor: | |
Standard hourly labor rate | $22 per hour |
Standard hours allowed per completed unit | 6.6 |
Actual labor hours worked | 183,000 |
Actual total labor costs | $4,020,000 |
Overhead: | |
Actual and budgeted fixed overhead | $1,029,600 |
Standard variable overhead rate | $24.50 per standard labor hour |
Actual variable overhead costs | $4,520,000 |
Overhead is applied on standard labor hours. The direct material price variance is:
22,800U | ||
22,800F | ||
52,000U | ||
52,000F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started