Question
The following data is received from your contractor on a projects key component: budgeted cost of work performed (BCWP) = $100 Budgeted cost of work
Budgeted cost of work scheduled (BCWS) = $200 Actual cost of work performed (ACWP) =100Budget at completion (BAC) = 500
Latest revised estimate (LRE) =900 which one of the earned value management (EVM) metrics can be determined from these data.
a. schedule performance index (SPI) = 2.,0 cost performance index (CPI) = 1.0, to complete performance index [TCPI](BAC) = 2.0
TCP (LRE) =1.0
b. SPI= 0.5, CPI=1.0 TCP(BAC)=2.0, TCP(LRE) = 0.5
c. SPI= 0.5, CPI=1.0 TCP(BAC)= 1.0, TCP(LRE) =0.5
d. SPI= 2.0, CPI=1.0 TCP(BAC)=1.0, TCP(LRE) =.1.0
Step by Step Solution
3.51 Rating (161 Votes )
There are 3 Steps involved in it
Step: 1
Schedule Variance Performed Plan 100 200 100Negative ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Matlab An Introduction with Applications
Authors: Amos Gilat
5th edition
1118629868, 978-1118801802, 1118801806, 978-1118629864
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App