Question

1 Approved Answer

The following data is received from your contractor on a projects key component: budgeted cost of work performed (BCWP) = $100 Budgeted cost of work

The following data is received from your contractor on a projects key component: budgeted cost of work performed (BCWP) = $100

Budgeted cost of work scheduled (BCWS) = $200 Actual cost of work performed (ACWP) =100Budget at completion (BAC) = 500

Latest revised estimate (LRE) =900 which one of the earned value management (EVM) metrics can be determined from these data. 

a. schedule performance index (SPI) = 2.,0 cost performance index (CPI) = 1.0, to complete performance index [TCPI](BAC) = 2.0

TCP (LRE) =1.0 

b. SPI= 0.5, CPI=1.0 TCP(BAC)=2.0, TCP(LRE) = 0.5

c. SPI= 0.5, CPI=1.0 TCP(BAC)= 1.0, TCP(LRE) =0.5 

d. SPI= 2.0, CPI=1.0 TCP(BAC)=1.0, TCP(LRE) =.1.0


Step by Step Solution

3.51 Rating (161 Votes )

There are 3 Steps involved in it

Step: 1

Schedule Variance Performed Plan 100 200 100Negative ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Matlab An Introduction with Applications

Authors: Amos Gilat

5th edition

1118629868, 978-1118801802, 1118801806, 978-1118629864

More Books

Students also viewed these Accounting questions