The following data pertain to operations at The Lego Group: Throughput Time Delivery Cycle Time Process Time ..... Move Time ....... Inspection Time. Queue Time......
The following data pertain to operations at The Lego Group: Throughput Time Delivery Cycle Time Process Time ..... Move Time ....... Inspection Time. Queue Time...... 10 hours 14 hours 3 hours 4 hours 1 hour .2 hours The wait time for this operation would be O a. 2 hours b. 3 hours C. 4 hours O d. 1 hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1