The following data pertain to the current year: Budgeted manufacturing overhead: OMR 450,000 Actual manufacturing overhead: OMR 390,000 Budgeted machine hours: 30,000 hrs. Actual machine
The following data pertain to the current year: Budgeted manufacturing overhead: OMR 450,000 Actual manufacturing overhead: OMR 390,000 Budgeted machine hours: 30,000 hrs. Actual machine hours: 33,000 hrs. Overhead applied to production totaled: