The following data relate to direct labor costs for February: Actual costs 7,700 hours at $14.00 Standard costs 7,000 hours at $15.00 1. What is
The following data relate to direct labor costs for February:
Actual costs | 7,700 hours at $14.00 |
Standard costs | 7,000 hours at $15.00 |
1. What is the direct labor rate variance?
a. | $7,000 favorable |
b. | $7,000 unfavorable |
c. | $7,700 favorable |
d. | $7,700 unfavorable |
2. What is the total direct labor variance?
a. $2,800F
b. $2,800U
c. $7,700U
d. none of the above