Question

1 Approved Answer

The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.99; actual, $2.03 Standard yards per unit: standard, 4.60 yards;

The following data relate to direct materials costs for February:

Materials cost per yard: standard, $1.99; actual, $2.03

Standard yards per unit: standard, 4.60 yards; actual, 5.28 yards

Units of production: 9,400

Calculate the direct materials quantity variance.

$12,975.76 unfavorable

$12,720.08 unfavorable

$12,720.08 favorable

$12,975.76 favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Business

Authors: Peter Scott

3rd Edition

0198807791, 978-0198807797

Students also viewed these Accounting questions