The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.99; actual, $2.05 Yards per unit: standard, 4.72 yards; actual,

The following data relate to direct materials costs for February:

Materials cost per yard: standard, $1.99; actual, $2.05

Yards per unit: standard, 4.72 yards; actual, 4.94 yards

Units of production: 9,100

The direct materials quantity variance is

a.$3,983.98 favorable

b.$3,983.98 unfavorable

c.$4,104.10 favorable

d.$4,104.10 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Chapters 1-13

Authors: Carl Warren

27th Edition

1337272108, 978-1337272100

More Books

Students also viewed these Accounting questions

Question

How did the authors avoid the post hoc fallacy?

Answered: 1 week ago

Question

The relevance of the information to the interpreter

Answered: 1 week ago

Question

The background knowledge of the interpreter

Answered: 1 week ago