The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93; actual, $2.05 Yards per unit: standard, 4.67 yards; actual,
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93; actual, $2.05 Yards per unit: standard, 4.67 yards; actual, 5.26 yards Units of production: 9,500 The direct materials quantity variance is
a. $11,490.25 unfavorable
b. $10,817.65 favorable
c. $11,490.25 favorable
d. $10,817.65 unfavorable