The following data was obtained from a WAN project: Activity Duration Predecessors A 3 Days --- B 6 Days --- C 3 Days A D

The following data was obtained from a WAN project:

Activity Duration Predecessors
A 3 Days ---
B 6 Days ---
C 3 Days A
D 2 Days B
E 3 Days B
F 1 Day C, D
G 5 Days C, D
H 4 Days E, F, G
I 7 Days E, F
  1. Construct a network diagram for the project. MS Excel, Word, or MS Project (1 pt)
  2. Calculate the scheduled completion time and identify the critical path. (2 pts)
  3. What is the slack time (float) for activities A, D, E, and F?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Operational Risk Management

Authors: Simon Ashby

1st Edition

1398605042, 978-1398605046

More Books

Students also viewed these General Management questions

Question

Then the value of ???? is (a) 18 (b) 92 (c)910 (d) 94 (e)32

Answered: 1 week ago