The following data was obtained from a WAN project: Activity Duration Predecessors A 3 Days --- B 6 Days --- C 3 Days A D
The following data was obtained from a WAN project:
Activity | Duration | Predecessors |
A | 3 Days | --- |
B | 6 Days | --- |
C | 3 Days | A |
D | 2 Days | B |
E | 3 Days | B |
F | 1 Day | C, D |
G | 5 Days | C, D |
H | 4 Days | E, F, G |
I | 7 Days | E, F |
- Construct a network diagram for the project. MS Excel, Word, or MS Project (1 pt)
- Calculate the scheduled completion time and identify the critical path. (2 pts)
- What is the slack time (float) for activities A, D, E, and F?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started