Question
The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network: Activity Duration Predecessors Task Budget A 3
The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network:
Activity Duration Predecessors Task Budget A 3 Days --- $4,920 B 6 Days --- $7,680 C 3 Days A $15,140 D 2 Days B $3,980 E 3 Days B $5,630 F 2 Days C, D $2,270 At the end of Day 7, the status of the project is as follows: Activity % Complete Actual Cost A 100% $4,200 B 100% $8,740 C 100% $18,250 D 75% $2,600 E 10% $560 F 0% $0 (a) Calculate the Cost and Schedule Variances and Indexes for tasks A, B, C, D, and E.
(b) As project manager, write a brief summary of the status of the project at this time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started