Question
The following details have been extracted from the standard cost card for product X: (/unit) Variable overhead 4 machine hours at 8.00/hour 32.00 2 labour
The following details have been extracted from the standard cost card for product X:
(/unit)
Variable overhead
4 machine hours at 8.00/hour 32.00
2 labour hours at 4.00/hour 8.00
Fixed overhead 20.00
During October 5450 units of the product were made compared to a budgeted production target of 5500 units. The actual overhead costs incurred were:
Machine-related variable overhead 176 000
Labour-related variable overhead 42 000
Fixed overhead 109 000
The actual number of machine hours was 22 000 and the actual number of labour hours was 10 800.
Required:
(a) Calculate the overhead cost variances in as much detail as possible from the data provided.
(b) Explain the meaning of, and give possible causes for, the variable overhead variances which you have calculated.
(c) Explain the benefits of using multiple activity bases for variable overhead absorption
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started