The following diagram is the original plan for a project. In reference to the diagram below answer the questions below. All durations are in
The following diagram is the original plan for a project. In reference to the diagram below answer the questions below. All durations are in weeks. DESIGN STRUCTURAL 37CCL 8.1 8.2 8.3 8.4 8.5 2 DESIGN BLOLDING DESIGN MOCH E PLOPNENT 6 13 TABRICATE CRECT STRUCTURAL 31CEL 10 FABRICATE MECHANICAL [QUIPMENT 9 JESIGN CLECT. EQLOPNENT 2 DESIGN INTEROR Identify the critical path. TAB ELECT. COUIPMENT 7 CONSTRUCT BUILDING 6 INSTALL MECH COLOPMENT 6 INSTALL ELEC1, CQUIPMENT 14 5 CONSTRUCTION INTERIOR CO-ORDINATE OWNERS. EQLOPNENT INSTALLATION 6 How many weeks can the Task "Fabricate Mechanical" be delayed before it causes any problems to the final completion of the project? Quantify your answer. If "Construction Building" is delayed by 8 weeks will this cause any problems to the final completion of the project? Quantify your answer. If "Construct Interiors" is delayed by 3 weeks will this cause any problems to the final completion of the project? Do not consider proposed change in Part 8.3 and quantify your answer. If "Construct Building" and "Construct Interiors are both delayed as outlined in 8.3 and 8.4 above will this cause any problems to the final completion of the project? Quantify your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
81 Identify the critical path To identify the critical path we need to calculate the earliest start time EST and latest start time LST for each activity Then well be able to find which activities have ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3