The following estimates have been prepared for a project: Fixed costs: $20,000 Depreciation: $10,000 Sales price: $2
Fantastic news! We've Found the answer you've been seeking!
Question:
The following estimates have been prepared for a project:
Fixed costs: $20,000
Depreciation: $10,000
Sales price: $2
Accounting break-even: 60,000 units
What must be the variable cost per unit?