The following events occurred during week 1: 1) Actual demand during week 1 was indeed 25 units. 2) Only 45 units of the planned MPS
The following events occurred during week 1:
1) Actual demand during week 1 was indeed 25 units.
2) Only 45 units of the planned MPS was produced.
3) Marketing forecasted that 40 units would be needed for week 9.
Provide an updated MPS table that you will see in the beginning of week 2. Note that, in your new MPS table, previous week 2 is now relabeled as week 1, etc., and week 9 is relabeled as week 8.
\begin{tabular}{|l|c|c|c|c|c|c|c|c|c} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\ \hline Forecast & 20 & 20 & 20 & 30 & 30 & 25 & 25 & 30 \\ \hline Orders & 25 & 23 & 12 & 18 & 16 & 10 & 5 & \\ \hline Projected Available Balance & 20 & 45 & 22 & 10 & 30 & 0 & 25 & 0 & 20 \\ \hline Available to Promise & 10 & & & 16 & & 35 & & 50 \\ \hline MPS & 50 & & & 50 & & 50 & & 50 \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started