Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following five activities are on the critical path of a project and their durations and distributions are specified below: Activity Duration (mean/mode) Distribution A
The following five activities are on the critical path of a project and their durations and distributions are specified below: Activity Duration (mean/mode) Distribution A 6 Normal with standard deviation 1.5 B 9 Triangular with max = 13, min = 7 C 14 Normal with standard deviation 3 D 12 Normal with standard deviation 2 E 17 Triangular with max = 20, min = 12 The project manager calculates the length of the critical path by summing the durations of the five activities: 6 + 9 + 14 + 12 + 17 = 58. The project sponsor would like to know how likely the project is to finish in less than 62 days. Calculate this likelihood using Crystal Ball? (You may assume that all other begin-end paths will E.) 0 Almost 100% O Roughly 90% O Roughly 80% O Roughly 60%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started