Question
1 Approved Answer
The following four months of data were collected on utility cost and the number of labor hours in a factory. Month Utility cost Labor hours
The following four months of data were collected on utility cost and the number of labor hours in a factory.
Month | Utility cost | Labor hours |
January | $68,200 | 1,800 |
February | 61,650 | 1,440 |
March | 69,400 | 1,860 |
April | 58,750 | 1,150 |
Using the high-low method, compute the variable rate for the utility cost. Please round to two decimal places.