The following four months of data were collected on utility cost and the number of labor hours in a factory.

Month Utility cost Labor hours
January $68,200 1,800
February 61,650 1,440
March 69,400 1,860
April 58,750 1,150

Using the high-low method, compute the variable rate for the utility cost. Please round to two decimal places.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting An Introduction

Authors: Eddie McLaney, Peter Atrill

3rd Edition

0273688227, 978-0273688228

More Books

Students explore these related Accounting questions