The following image shows an Activity-on-Arrow network for a simple project (assume all durations are in days). Answer the following questions: (a) List

The following image shows an Activity-on-Arrow network for a simple project (assume all durations are in days).

 

Answer the following questions:

(a)    List all the paths through this network. (3 mark)

(b)    What is the critical path? (3 mark)

(c)     What is the duration of the project? (1 mark)

(d)    What would be the effect on the project completion date if task K took 3 days instead of 2 days? (1 mark)

(e)    What would be the effect on the project completion date if task C took 5 days instead of 4 days? (1 mark)

A = 1 1 B=3 C = 4 2 3 4 D=4 E=2 F = 3 5 G=2 1=6 H = 2 6 01 J = 1 7 K=2 8 L = 3 M = 3 

A = 1 1 B=3 C = 4 2 3 4 D=4 E=2 F = 3 5 G=2 1=6 H = 2 6 01 J = 1 7 K=2 8 L = 3 M = 3

Step by Step Solution

3.34 Rating (172 Votes )

There are 3 Steps involved in it

Step: 1

Answer a The paths through this network are ABEFIM ABEGHJKM ABEGHLM ACDGHJKM ACDGHLM b The critical ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these Computer Network questions

Question

Imagine yourself participating in a

Answered: 1 week ago

Question

Briefly describe each of the seven basic quality' tools.

Answered: 1 week ago