The following image shows an Activity-on-Arrow network for a simple project (assume all durations are in days). Answer the following questions: (a) List
The following image shows an Activity-on-Arrow network for a simple project (assume all durations are in days).
Answer the following questions:
(a) List all the paths through this network. (3 mark)
(b) What is the critical path? (3 mark)
(c) What is the duration of the project? (1 mark)
(d) What would be the effect on the project completion date if task K took 3 days instead of 2 days? (1 mark)
(e) What would be the effect on the project completion date if task C took 5 days instead of 4 days? (1 mark)
A = 1 1 B=3 C = 4 2 3 4 D=4 E=2 F = 3 5 G=2 1=6 H = 2 6 01 J = 1 7 K=2 8 L = 3 M = 3
Step by Step Solution
★★★★★
3.34 Rating (172 Votes )
There are 3 Steps involved in it
Step: 1
Answer a The paths through this network are ABEFIM ABEGHJKM ABEGHLM ACDGHJKM ACDGHLM b The critical ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started