[ The following information applies to the questions displayed below. ] In 2 0 2 4 , the Westgate Construction Company entered into a contract

[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,523,000 $ 3,177,000 $ 1,980,000
Estimated costs to complete as of year-end 6,177,0001,800,0000
Billings during the year 2,070,0003,630,0004,300,000
Cash collections during the year 1,835,0003,400,0004,765,000
Westgate recognizes revenue over time according to percentage of completion.
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.
202420252026
Costs incurred during the year $ 2,523,000 $ 3,835,000 $ 4,005,000
Estimated costs to complete as of year-end 6,177,0004,170,0000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Analysis Synthesis And Design Of Chemical Processes

Authors: Richard Turton, Joseph Shaeiwitz, Debangsu Bhattacharyya, Wallace Whiting

5th Edition

0134177401, 978-0134177403

Students also viewed these Accounting questions