Question
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,291,000 | $ | 3,555,000 | $ | 2,259,400 | |||
Estimated costs to complete as of year-end | 5,609,000 | 2,054,000 | 0 | ||||||
Billings during the year | 2,110,000 | 3,736,000 | 4,154,000 | ||||||
Cash collections during the year | 1,855,000 | 3,500,000 | 4,645,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
- Req 2A
- Req 2B
- Req 2C
In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Journal entry worksheet
- Record construction costs.
Note: Enter debits before credits.
|
- Req 2A
- Req 2B
- Req 2C
In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Journal entry worksheet
- Record construction costs.
Note: Enter debits before credits.
|
- Req 2A
- Req 2B
- Req 2C
In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Journal entry worksheet
- Record construction costs.
Note: Enter debits before credits.
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started