[The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 2023 $2,175,800 0 3,378,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round Intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) Costs incurred during the year Estimated costs to complete as of year-end 2021 2022 2023 $2,580,000 $3,830,000 $3,230,000 6,020,000 3,130,000 2021 2022 2023 Revenue Gross profit (los) The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 Cost incurred during the year $2,580,000 $4,042,000 Estimated costs to complete as of year-end $2,175,800 6,020,000 1,978,000 Billings during the year 2,060,000 4,562,000 3,370,000 Cash collections during the year 1,830,000 4,200,000 3.970,000 2023 Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round Intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Coats Sneurred during the year $2,580,000 $3,030,000 53,990,000 Estimated costs to complete as of year-end 6,020,000 4.160.000 o 2021 2022 2023 Revenue Gross profit doss)