Question
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $7 per pound $ 35 Direct labor: 3 hours at $16 per hour 48 Variable overhead: 3 hours at $4 per hour 12 Total standard cost per unit $ 95 The planning budget for March was based on producing and selling 30,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs: Purchased 175,000 pounds of raw materials at a cost of $6.80 per pound. All of this material was used in production. Direct laborers worked 71,000 hours at a rate of $17 per hour. Total variable manufacturing overhead for the month was $340,090. Foundational 10-8 (Algo)
8. What direct labor cost would be included in the companys flexible budget for March? [The following information applies to the questions displayed below.]
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $7 per pound $ 35 Direct labor: 3 hours at $16 per hour 48 Variable overhead: 3 hours at $4 per hour 12 Total standard cost per unit $ 95 The planning budget for March was based on producing and selling 30,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs: Purchased 175,000 pounds of raw materials at a cost of $6.80 per pound. All of this material was used in production. Direct laborers worked 71,000 hours at a rate of $17 per hour. Total variable manufacturing overhead for the month was $340,090. Foundational 10-6 (Algo)
6. If Preble had purchased 186,000 pounds of materials at $6.80 per pound and used 175,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $7 per pound $ 35 Direct labor: 3 hours at $16 per hour 48 Variable overhead: 3 hours at $4 per hour 12 Total standard cost per unit $ 95 The planning budget for March was based on producing and selling 30,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs: Purchased 175,000 pounds of raw materials at a cost of $6.80 per pound. All of this material was used in production. Direct laborers worked 71,000 hours at a rate of $17 per hour. Total variable manufacturing overhead for the month was $340,090. Foundational 10-5 (Algo)
5. If Preble had purchased 186,000 pounds of materials at $6.80 per pound and used 175,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $7 per pound $ 35 Direct labor: 3 hours at $16 per hour 48 Variable overhead: 3 hours at $4 per hour 12 Total standard cost per unit $ 95 The planning budget for March was based on producing and selling 30,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs: Purchased 175,000 pounds of raw materials at a cost of $6.80 per pound. All of this material was used in production. Direct laborers worked 71,000 hours at a rate of $17 per hour. Total variable manufacturing overhead for the month was $340,090. Foundational 10-9 (Algo)
9. What is the labor rate variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started