The following information belongs to Al Yaqoobi Manufacturing Company that uses a standard costing system: Basic wage rate: OMR12 per hour Fringe benefits: OMR2 per
The following information belongs to Al Yaqoobi Manufacturing Company that uses a standard costing system: Basic wage rate: OMR12 per hour Fringe benefits: OMR2 per hour Basic time: 2 hours per unit Allowance for down time: 0.3 hours per unit Allowance for brakes: 0.2 hours per unit Based on the above information, what is the standard direct labour cost per unit? O a. OMR 32.200 O b. b. OMR 28.000 O c. OMR 35.000 O d. OMR 30.000