Question

1 Approved Answer

The following information concerns two jobs Item Job 557E Units produced 220 Standard per unit Direct materials quantity 8 kg Material Price $4.50 per

The following information concerns two jobs Item Job 557E Units produced 220 Standard per unit Direct materials quantity 8 kg Material Price $4.50 per kg Direct labour hours 2 hours Labour rate $12 per hour Actual consumption Direct materials quantity 1,500 Materials Price $5 per kg Direct labour hours 550 hours Labour rate $10.50 per hour Job 235Q 160 4 kg $3 per kg 2.5 hour $19 per hour (e) (f) (g) (h) Variances Material price (a) $150 F Material quantity (b) $90 F Labour rate (c) $425 U Labour efficiency (d) $475 U Requirements: Determine the missing amounts for items (a) through (h). Show all calculations (2.5 marks each)

Step by Step Solution

3.41 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

For Job 557E a Direct material price variance Actual quantity used Standard priceActual Price Standa... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: William K. Carter

14th edition

759338094, 978-0759338098

More Books

Students also viewed these Accounting questions