The following information corresponds to the activities of a project. Answer the following questions using the CPM method. Actividad Predeceder Tiempo A A 3 A
The following information corresponds to the activities of a project. Answer the following questions using the CPM method. Actividad Predeceder Tiempo A A 3 A S B, C D H Project duration Critical path write it without spaces for example: ABCDE Activity clearance E Last time to finish activity B If activity E changes from 6 to 10, what is the duration of the project