The following information for a recent project was taken from the records of Glory Company: Days Process Time15.0 Inspection0.5 Waiting Time From order receipt until
The following information for a recent project was taken from the records of Glory Company:
Days
Process Time15.0
Inspection0.5
Waiting Time
From order receipt until start of production6.0
From start of production through project completion3.0
Move Time1.5
Required:
1.How long did it take to complete the project once production commenced?
2.Compute the manufacturing cycle efficiency.
3.As judged by the cycle efficiency, what percentage of the overall production time was spent on (1) value adding activities and (2) non-value adding activities?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 To determine how long it took to complete the project once production commenced we need to add up ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started