The following information is available for a company's utility cost for operating its machines over the last four months. Month Machine hours Utility cost January
The following information is available for a company's utility cost for operating its machines over the last four months.
Month | Machine hours | Utility cost | ||
January | 1,000 | $ | 6,000 | |
February | 1,900 | $ | 7,100 | |
March | 2,600 | $ | 8,100 | |
April | 700 | $ | 4,350 | |
Using the high-low method, the estimated variable cost per machine hour for utilities is:
Multiple Choice
-
$3.12.
-
$4.12.
-
$5.50.
-
$1.97.
-
$6.21.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started