The following information is for the third quarter of this year: Planned Actual Production 80,000 units 81,000 units Direct Material Purchases 225,000 lbs. @ $

The following information is for the third quarter of this year:

Planned Actual

Production 80,000 units 81,000 units

Direct Material Purchases 225,000 lbs. @ $ 3.00 225,000 lbs. @ $ 2.90

Direct Material Used 200,000 lbs. @ $ 3.00 200,500 lbs. @ $ 2.90

Direct labor 160,000 hrs. @ $ 10.00 140,000 hrs. @ $ 12.00

Variable manufacturing overhead $ 200,000 $ 202,000

Fixed manufacturing overhead $ 721,000 $ 723,500

Standard direct material pounds per unit 2.5

Standard direct labor hour per unit 2.0

Variable Overhead Rate per direct labor hour $ (VOH = Budgeted Variable Overhead / Budget Input)

Required: Calculate the following overhead variances; overhead is allocated based on direct labor hours.

  1. Overhead volume variance
  2. Overhead efficiency variance
  3. Overhead spending variance
  4. Formulate a hypothesis about the cause of these variances

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions