Question
The following information is provided on a project as at the end of 8 months. Assume that the cost of each activity is linearly distributed
The following information is provided on a project as at the end of 8 months. Assume that the cost of each activity is linearly distributed over its duration.
Activity |
Duration (months) |
Predecessors |
Total Budgeted Cost ($) |
% complete after 8 months |
A |
2 |
- |
800 |
100 |
B |
6 |
A |
3600 |
80 |
C |
5 |
A |
1500 |
100 |
D |
4 |
B |
1600 |
- |
E |
3 |
C |
900 |
66.7 |
F |
3 |
D, E, G |
600 |
- |
G |
1 |
A |
600 |
0 |
If data from time sheets and other accounting records indicate that the actual amount of money spent on the project so far (i.e. at the end of 8 months) is $6,900, determine the following for the entire project
- the cost variance,
- schedule variance,
- time variance,
- cost performance index,
- schedule performance index,
- critical ratio for this project.
- New budget if trend continues
- New project duration if trend continues
Be sure to interpret your results and comment on the status of the project.
This assignment should be done in Excel. Please show formulas needed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started