Question
The Following information relates to contract #102,which was undertaken for the construction of a railway bridge for the Kampton Council.The Value of the contract is
The Following information relates to contract #102,which was undertaken for the construction of a railway bridge for the Kampton Council.The Value of the contract is $250000 and it is at a stage where profits can be attributed to it.Details of the contract are shown in the books:
$
Materials sent to site 85349
Labour engaged on site 74375
Plant installed at cost 15000
Direct expenditure 4136
General Overhead Charges 3167
Materials returned to store 549
Work certified 195000
Cost of Work not certified 4500
Materials on hand,December 31 1883
Wages accrued on December 31 2400
Direct Expenditure 240
Value of Plant December 31 11000
Cash has been received from the contractee,amounting to $180000
Required: (i)contract Account
(ii) profit and loss account
(iii)contractee accounts
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started