The following information relates to Job #2042: Direct materials placed into production Direct labour cost Machine hours worked $9,000 $4,500 100 hours Factory overhead rate
The following information relates to Job #2042: Direct materials placed into production Direct labour cost Machine hours worked $9,000 $4,500 100 hours Factory overhead rate is $22.50 per machine hour. What is the total amount assigned to Job #2042? 1) $9,000 2) $15,750 3) $13,500 4) $20,250