Question
The following information relates to Lancashire Manufacturing: To produce a unit of product: Mixing department 3 minutes per unit Molding department 5 minutes per unit
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department | 3 minutes per unit |
Molding department | 5 minutes per unit |
Casting department | 7 minutes per unit |
Finishing department | 4 minutes per unit |
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
a.415 minutes
b.35 minutes
c.380 minutes
d.None of these choices are correct.
The following information relates to Cranmore Manufacturing: To produce a unit of product:
Cutting department | 5 minutes per unit |
Welding department | 8 minutes per unit |
Polishing department | 3 minutes per unit |
Finishing department | 4 minutes per unit |
There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes. What is the cycle time of operation?
a.20 minutes
b.60 minutes
c.35 minutes
d.16 minutes
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started