Question
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration perweek:
Activity | Duration (weeks) | Precedes | Crash Cost/Week |
A (start) | 3 | B, C | $370 |
B | 2 | E | $110 |
C | 4 | F | $200 |
E | 1 | F | $160 |
F (end) | 2 | $420 |
Part 2Suppose that Rafay is only given
7
weeks (instead of
9)
to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.
Activity | Each Activity Should be Reduced BY (weeks) |
A B C E F | enter your response here week(s) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started