The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: + Duration (weeks) 2 Activity A (start) B C E (end) Suppose that Rafay is only given 9 weeks (instead of 12) to complete the project. By how many weeks should 2624 Crash Cost/Week Precedes B, C E F F $370 $130 $220 $160 $420