Question
The following is an actual previous midterm exam question that focused on networks, critical paths and slack times. Complete individually and hand in before the
The following is an actual previous midterm exam question that focused on networks, critical paths and slack times. Complete individually and hand in before the beginning of next class (Monday, Feb 14th, 12pm (noon)
Show all your work
- a) Given the following activities, predecessors, and times, draw a critical path network diagram (5 marks)
- b) What is the critical path? (3 marks)
- c) How long will it take to complete the project? (2 marks)
- d) What is the slack time for activity C? (2 marks)
- e) What is the slack time for activity I? (2 marks)
Activity Immediate Predecessor Time (days)
A - 3
B - 2
C - 6
D B 5
E A 3
F A 5
G E & D 4
H C 2
I F & G 4
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started