The following is the details of the cost at 70% capacity of Aaron company. It is expected that the company can produce 25,000 units in
The following is the details of the cost at 70% capacity of Aaron company. It is expected that the company can produce 25,000 units in 3 months which represents 100% of the capacity.
Supplies | OMR 1400 |
Power | OMR 7000 |
Insurance | OMR 4200 |
Maintenance | OMR 4900 |
Depreciation | OMR 18,000 |
Supervision | OMR 57,000 |
Total costs | OMR 92,500 |
Units produced at 70% capacity | 17,500 |
From the above table the first four costs are completely variable and the remaining are fixed. Prepare a flexible budget for 70% and 100% capacity.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started