The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh

The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to the names of clients and contract numbers. Compute all times based on initiating work on day 241.

Job

Date Job Received

Due Date

Duration (days)

BR02

230

320

35

CX01

235

360

40

DE06

231

310

30

RG05

228

300

15

SY11

225

270

25

a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table):

Sequence

Job

1

Part 2

2

Part 3

3

Part 4

4

Part 5

The average tardiness (job lateness) for the sequence developed using the FCFS rule =

days (round your response to two decimal places).

Part 6

The average completion time (flow time) for the sequence developed using the FCFS rule =

days (round your response to two decimal places).

Part 7

The percentage utilization for the sequence developed using the FCFS rule =

(enter your response as a percentage rounded to two decimal places).

Part 8

b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

Part 9

2

Part 10

3

Part 11

4

Part 12

The average tardiness (job lateness) for the sequence developed using the SPT rule =

days (round your response to two decimal places).

Part 13

The average completion time (flow time) for the sequence developed using the SPT rule =

days (round your response to two decimal places).

Part 14

The percentage utilization for the sequence developed using the SPT rule =

(enter your response as a percentage rounded to two decimal places).

Part 15

c) Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

Part 16

2

Part 17

3

Part 18

4

Part 19

The average tardiness (job lateness) for the sequence developed using the LPT rule =

days (round your response to two decimal places).

Part 20

The average completion time (flow time) for the sequence developed using the LPT rule =

days (round your response to two decimal places).

Part 21

The percentage utilization for the sequence developed using the LPT rule =

(enter your response as a percentage rounded to two decimal places).

Part 22

d) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

Part 23

2

Part 24

3

Part 25

4

Part 26

The average tardiness (job lateness) for the sequence developed using the EDD rule =

days (round your response to two decimal places).

Part 27

The average completion time (flow time) for the sequence developed using the EDD rule =

days (round your response to two decimal places).

Part 28

The percentage utilization for the sequence developed using the EDD rule =

(enter your response as a percentage rounded to two decimal places).

Part 29

e) Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is:

Sequence

Job

1

Part 30

2

Part 31

3

Part 32

4

Part 33

The average tardiness (job lateness) for the sequence developed using the CR rule =

days (round your response to two decimal places).

Part 34

The average completion time (flow time) for the sequence developed using the CR rule =

days (round your response to two decimal places).

Part 35

The percentage utilization for the sequence developed using the CR rule =

(enter your response as a percentage rounded to two decimal places).

Part 1

An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day

205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Working In Teams Moving From High Potential To High Performance

Authors: Brian A. Griffith ,Ethan B. Dunham

1st Edition

1452286302, 978-1452286303

More Books

Students also viewed these General Management questions