The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh

The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.

Job

Date Job Received

Due Date

Duration (days)

BR02

230

320 35

CX01

235

360

40

DE06

231

310

30

RG05

228

300

15

SY11

225

270

25

Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:

Sequence

Job

1

??

2

??

3

??

4

??

5

??

The total flow time for the sequence developed using the FCFS rule =??? days (round your response to two decimal places).

The percentage utilization for the sequence developed using the FCFS rule =??? %%%(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the FCFS rule =??? jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the FCFS rule =??? days (round your response to two decimal places).

Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

??

2

??

3

??

4

??

5

??

The total flow time for the sequence developed using the EDD rule =????? days (round your response to two decimal places).

The percentage utilization for the sequence developed using the EDD rule =??? %(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the EDD rule =?? jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the EDD rule =??? days (round your response to two decimal places).

Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

??

2

??

3

??

4

??

5

??

The total flow time for the sequence developed using the SPT rule =?? days (round your response to two decimal places).

The percentage utilization for the sequence developed using the SPT rule =?? %(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the SPT rule =???? jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the SPT rule =??? days (round your response to two decimal places).

Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence

Job

1

??

2

??

3

??

4

??

5

??

The total flow time for the sequence developed using the LPT rule = ???? days (round your response to two decimal places).

The percentage utilization for the sequence developed using the LPT rule =???? %%(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the LPT rule =??? jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the LPT rule =??? days (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial accounting

Authors: ramji balakrishnan, k. s i varamakrishnan, Geoffrey b. sprin

1st edition

471467855, 978-0471467854

More Books

Students also viewed these Accounting questions

Question

2. What factors infl uence our perceptions?

Answered: 1 week ago

Question

4. Does mind reading help or hinder communication?

Answered: 1 week ago