The following labour standards have been established for a product: Standard labour hours per unit of output 7.5hours Standard labour rate $15.25per hour The following
The following labour standards have been established for a product:
Standard labour hours per unit of output 7.5hours Standard labour rate $15.25per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked 9,600hours Actual total labour cost $144,480Actual units of output 1,200
What is the labour efficiency variance for the month?
Multiple Choice
- $7,230 U.
- $7,230 F.
- $9,150 F.
- $9,150 U.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started