The following list of jobs in a critical department includes estimates of their required times: JOB REQUIRED TIME (DAYS) DAYS TO DELIVERY PROMISE SLACK A

The following list of jobs in a critical department includes estimates of their required times:

JOB REQUIRED TIME (DAYS) DAYS TO DELIVERY PROMISE SLACK
A 1 6 5
B 11 5 6
C 8 10 2
D 6 9 3
E 15 4 (late) 19
F 3 6 3
G 2 7 (late) 9
H 4 6 2

a. Use the shortest operation time rule to schedule these jobs. What is the mean flow time? (Round your answer to 3 decimal places.)

b. The boss does not like the schedule in a. Jobs E and G must be done first, for obvious reasons. (They are already late.) Reschedule the jobs by assigning E and G first and second, respectively, and then assigning the remaining jobs using the shortest operation time rule. What is the new mean flow time? (Round your answer to 3 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Your Sacred Work A Call To Spiritual Entrepreneurship

Authors: Dru Dodson

1st Edition

979-8988712404

More Books

Students also viewed these General Management questions