Question
The following materials standards have been established for a particular product: Standard quantity per unit of output 3.6 metre Standard price $10.20 per metre The
The following materials standards have been established for a particular product:
Standard quantity per unit of output 3.6 metre
Standard price $10.20 per metre
The following data pertain to operations concerning the product for the last month:
Actual materials purchased 7,100 metres
Actual cost of materials purchased $68,515
Actual materials used in production 6,600 metres
Actual output 1,780 units
The following labour standards have been established for a particular product:
Standard labour hours per unit of output 2.8 hours
Standard labour rate $11.50 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worker 6,900 hours
Actual total labour cost $80,385
Actual output 2,300 units
Required:
a) What was the materials price variance for the month?
b) What was the materials quantity variance for the month?
c) What was the labour rate variance for the month?
d) What was the labour efficiency variance for the month?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started