The following precedence chart, Table 1.2, was also given to Pete by his boss. His boss has asked him to balance the line using line
The following precedence chart, Table 1.2, was also given to Pete by his boss. His boss has asked him to balance the line using line balancing techniques. Construct the precedence diagram for Pete, calculate flow time and the minimum theoretical workstations, then group activities together to form workstations that do not violate cycle time or precedence requirements, calculate the efficiency for your workstation groupings, and explain if idle time exists and where it would be. Pete's boss has informed him that the desired cycle time is 6 minutes.
Table 1.2 Precedence Chart Activity Time Precedent A-Visual Check on CD 4 B-Load Software Files 2 C-Initiate Burn Sequence B D-Burn CD A, C E-Package Finished CD 6 D, F F-Print CD Label 2Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started