Question

1 Approved Answer

The following precedence chart, Table 1.2, was also given to Pete by his boss. His boss has asked him to balance the line using line

The following precedence chart, Table 1.2, was also given to Pete by his boss. His boss has asked him to balance the line using line balancing techniques. Construct the precedence diagram for Pete, calculate flow time and the minimum theoretical workstations, then group activities together to form workstations that do not violate cycle time or precedence requirements, calculate the efficiency for your workstation groupings, and explain if idle time exists and where it would be. Pete's boss has informed him that the desired cycle time is 6 minutes.

image text in transcribed
Table 1.2 Precedence Chart Activity Time Precedent A-Visual Check on CD 4 B-Load Software Files 2 C-Initiate Burn Sequence B D-Burn CD A, C E-Package Finished CD 6 D, F F-Print CD Label 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Time Management From The Inside Out

Authors: Julie Morgenstern

1st Edition

0805075909, 978-0805075908

More Books

Students also viewed these General Management questions

Question

What improvements would you make to the product?

Answered: 1 week ago

Question

Discuss cross-cultural differences in perception

Answered: 1 week ago

Question

Compare and contrast families and family roles across cultures

Answered: 1 week ago

Question

Compare and contrast sex and gender roles across cultures

Answered: 1 week ago