The following project activities have been defined with their required times for completion. Task ID Task predecessors Duration (days) A - 3 B A 4
The following project activities have been defined with their required times for completion.
Task ID | Task predecessors | Duration (days) |
A | - | 3 |
B | A | 4 |
C | A | 2 |
D | B | 5 |
E | C | 1 |
F | C | 2 |
G | D, E | 4 |
H | F, G | 3 |
a- Draw a network diagram for the activities.
b- Calculate the early start time and early finish time.
c- Calculate the late start time and late finish time.
d- Show the critical path.