The following project is at the end of its sixth week. Find the CPI and SPI. Show all work. Activity Predecessors Duration (wks) Budget ($)
The following project is at the end of its sixth week.
Find the CPI and SPI.
Show all work.
Activity | Predecessors | Duration (wks) | Budget ($) | Actual Cost ($) | % Complete |
a | - | 2 | 300 | 400 | 100 |
b | - | 3 | 200 | 180 | 100 |
c | a | 2 | 250 | 300 | 100 |
d | a | 5 | 600 | 400 | 20 |
e | b, c | 4 | 400 | 200 | 20 |