Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following report appeared in the press on 8 August 2019: The opening of the M4 East tunnel was several months later than planned,
The following report appeared in the press on 8 August 2019: "The opening of the M4 East tunnel was several months later than planned, resulting in the builder paying about $2 million to the toll road operator which owns the tunnel, as provided in the contract."
This need for the builder to pay agreed compensation for its delay in completion of the tunnel is an example of
a.
indemnity
b.
liquidated damages
c.
unliquidated damages
d.
resttution
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started