The following report appeared in the press on 8 August 2019: The opening of the M4 East tunnel was several months later than planned,

The following report appeared in the press on 8 August 2019: "The opening of the M4 East tunnel was several months later than planned, resulting in the builder paying about $2 million to the toll road operator which owns the tunnel, as provided in the contract."

This need for the builder to pay agreed compensation for its delay in completion of the tunnel is an example of

a.

indemnity

b.

liquidated damages

c.

unliquidated damages

d.

resttution

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

9781119563099

Students also viewed these Law questions