Question
1 Approved Answer
The following represents a project with known activity times. All times are in weeks Activity Immediate Predecessor time A - 4 B - 3 C
The following represents a project with known activity times. All times are in weeks
Activity Immediate Predecessor time
A - 4
B - 3
C A 2
D B 7
E C,D 4
F B 5
G E,F 4
Using the data in Table 13-4, what is the latest possible time that C may be started
without delaying completion of the project?
(a)0
(b)4
(c)8
(d)10
(e)none of the above