The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time (weeks) A - 5 B - 3
The following represents a project with known activity times. All times are in weeks.
Activity | Immediate Predecessor | Time (weeks) |
A | - | 5 |
B | - | 3 |
C | A | 5 |
D | B | 5 |
E | C, D | 1 |
F | B | 5 |
What is the minimum possible time required for completing the project (round it to the nearest whole number)?