Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following six jobs are to be scheduled on a single machine: Job 1 2 3 4 5 6 Processing time ( min . )

The following six jobs are to be scheduled on a single machine:
Job 123456
Processing time (min.)9015023010016070
Suppose the jobs are processed in FCFS numerical order. Compute the makespan, flow time for each job, and overall average flow time. Round your answers to the nearest whole number.
Job Flow Time (min)
1
2
3
4
5
6
Makespan:
minutes
Average flow time:
minutes
In what order would the jobs be processed using the SPT rule?
The SPT sequence is
-Select-
-
-Select-
-
-Select-
-
-Select-
-
-Select-
-
-Select-
.
Compute the average flow time after each job is completed. Round your answer to the nearest whole number.
Average flow time:
minutes
Compare this answer with your answer to part a.
The
-Select-
minimizes flow time and gets the most work done in the least amount of time.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And The Arts

Authors: William J. Byrnes

5th Edition

0415663296, 978-0415663298

More Books

Students also viewed these General Management questions