Question

1 Approved Answer

The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a

The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per -week basis.

  1. Determine the project cost and duration without crashing.

  1. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.

  2. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.

  3. Create a graph that shows project expediting cost plotted as a function of the reduction in project

duration.

Activity

Normal

Time

Crash

Time

Normal

Cost

Crash Cost

Predecessor

A

10

7

2000

2600

B

12

8

1500

2000

A

C

16

12

2200

3000

A

D

8

7

2500

3000

B

E

13

10

1950

2275

C

F

9

8

800

1000

D

G

24

29

3650

4000

E, F

H

17

14

1200

1800

G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting An Introduction

Authors: Eddie McLaney, Dr Peter Atrill, Eddie J. Mclan

5th Edition

0273733206, 978-0273733201

More Books

Students also viewed these Accounting questions