Question
The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a
The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per -week basis.
-
Determine the project cost and duration without crashing.
-
Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
-
Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
-
Create a graph that shows project expediting cost plotted as a function of the reduction in project
duration.
Activity | Normal Time | Crash Time | Normal Cost | Crash Cost | Predecessor |
A | 10 | 7 | 2000 | 2600 |
|
B | 12 | 8 | 1500 | 2000 | A |
C | 16 | 12 | 2200 | 3000 | A |
D | 8 | 7 | 2500 | 3000 | B |
E | 13 | 10 | 1950 | 2275 | C |
F | 9 | 8 | 800 | 1000 | D |
G | 24 | 29 | 3650 | 4000 | E, F |
H | 17 | 14 | 1200 | 1800 | G |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started